name: incident-response
|
|
description: "Manage active production incidents through detection, triage, mitigation, communication, and resolution with structured roles and decision-making. Use this skill whenever the user has an active incident, a production issue, a service outage, a security incident, or needs to plan incident response procedures. Triggers on incident response, production incident, outage, service down, site down, P0, P1, severity, downtime, on-call, incident commander, status page, postmortem prep. Also triggers when something is actively broken in production and the user is figuring out what to do."
|
|
category: operations
|
|
catalog_summary: "Incident triage, comms, mitigation, escalation"
|
|
display_order: 2
|
|
---
|
|
|
|
# Incident Response
|
|
|
|
Manage active production incidents from detection to resolution. Stack-agnostic. Tool-agnostic.
|
|
|
|
This skill is for active incidents and incident process. For after-the-fact analysis, use `after-action-report`. For planned launches, use `launch-runbook`.
|
|
|
|
---
|
|
|
|
## When to use
|
|
|
|
- An active incident is happening
|
|
- Building incident response procedures
|
|
- Defining severity levels
|
|
- Setting up on-call rotations
|
|
- Training a team on incident response
|
|
|
|
## When NOT to use
|
|
|
|
- Post-incident retrospective (use `after-action-report`)
|
|
- Planned launches (use `launch-runbook`)
|
|
- Pre-launch issue triage (use `qa-testing`)
|
|
|
|
---
|
|
|
|
## Required inputs
|
|
|
|
- Awareness of the incident (alert, customer report, internal observation)
|
|
- Access to production systems and monitoring
|
|
- Roles and authorities clearly defined
|
|
- Communication channels operational
|
|
|
|
---
|
|
|
|
## The framework: 5 phases
|
|
|
|
### 1. Detection
|
|
|
|
How the incident becomes known.
|
|
|
|
**Detection sources:**
|
|
|
|
- Automated alerts (monitoring, SLO violations, error rate spikes)
|
|
- Customer reports (support tickets, social media, status page subscribers)
|
|
- Internal observation (engineer notices something off)
|
|
- Third-party (security researchers, partners)
|
|
|
|
**On detection:**
|
|
|
|
- Acknowledge within target time (typically 5 to 15 minutes for critical)
|
|
- Assess severity (see severity rubric below)
|
|
- Page the on-call if not already paged
|
|
- Open the incident channel
|
|
|
|
### 2. Triage
|
|
|
|
Establish severity and impact.
|
|
|
|
**Severity rubric:**
|
|
|
|
| Severity | Definition | Response |
|
|
|---|---|---|
|
|
| SEV-1 (Critical) | Major customer-facing functionality broken. Data integrity at risk. Security breach. | All-hands. Incident commander. Active war room. Public communication required. |
|
|
| SEV-2 (Major) | Significant degradation. Some customers affected. Revenue impact. | Incident commander assigned. Active response. Internal communication. May or may not need public communication. |
|
|
| SEV-3 (Minor) | Limited impact. Workaround available. Affecting a small group of users. | Standard on-call response. Single owner. |
|
|
| SEV-4 (Low) | Cosmetic, edge-case, or low-frequency. No urgent action needed. | Tracked as bug. Addressed in normal queue. |
|
|
|
|
Severity can change. Re-evaluate as more info emerges.
|
|
|
|
### 3. Mitigation
|
|
|
|
Stop the bleeding before fixing the cause.
|
|
|
|
**Mitigation patterns (faster than full fix):**
|
|
|
|
- **Rollback** (revert recent deploy)
|
|
- **Feature flag off** (disable the broken feature without deploy)
|
|
- **Failover** (route to healthy replica or region)
|
|
- **Scale up** (more capacity to absorb the load)
|
|
- **Throttle** (reject some traffic to protect the rest)
|
|
- **Graceful degradation** (turn off non-essential features to keep core functional)
|
|
- **Maintenance mode** (last resort, blocks all users)
|
|
|
|
**Mitigation principle:** Stop user impact first. Cause analysis second.
|
|
|
|
### 4. Communication
|
|
|
|
Three audiences during an incident:
|
|
|
|
**Internal team:**
|
|
- Real-time updates in incident channel
|
|
- Cadence: every 15 minutes minimum during active incident
|
|
- Format: timestamped status updates with what we know, what we're doing, ETA
|
|
|
|
**Internal stakeholders:**
|
|
- Higher-level updates to broader org
|
|
- Cadence: every 30 to 60 minutes
|
|
- Format: business-impact framing, not technical detail
|
|
|
|
**External / customers:**
|
|
- Status page updates
|
|
- Cadence: every 30 minutes minimum during active incident
|
|
- Format: plain language, no blame, what users are experiencing, what to expect
|
|
|
|
**Communication principles:**
|
|
- Acknowledge before you have answers ("We're aware and investigating")
|
|
- Update on schedule even if no progress ("Still investigating, no new information")
|
|
- Never speculate publicly about cause
|
|
- Confirm resolution explicitly when restored
|
|
|
|
### 5. Resolution
|
|
|
|
Verified fix, customers restored, incident closed.
|
|
|
|
**Resolution criteria:**
|
|
|
|
- Mitigation in place and verified
|
|
- Root cause identified (or explicitly deferred to AAR)
|
|
- All affected systems back to normal
|
|
- Customers can resume normal use
|
|
- Final status update posted (internal and external)
|
|
- Incident channel can be closed (or archived for AAR)
|
|
|
|
After closure:
|
|
- Schedule AAR within 1 to 2 weeks
|
|
- Capture initial timeline while memories are fresh
|
|
- Track follow-up action items
|
|
|
|
---
|
|
|
|
## Roles during an incident
|
|
|
|
| Role | Responsibility |
|
|
|---|---|
|
|
| Incident commander (IC) | Owns the response. Calls decisions. Assigns work. Not necessarily the most technical person; needs to coordinate. |
|
|
| Communications lead | Owns internal and external messaging. Reduces IC's communication burden. |
|
|
| Operations lead | Drives the technical investigation and mitigation. Often the most senior on-call engineer. |
|
|
| Scribe | Captures the timeline as the incident unfolds. Critical for AAR. |
|
|
| Subject matter experts | Pulled in as needed. Service owners, database experts, security experts. |
|
|
|
|
For small teams or low-severity incidents, one person can hold multiple roles. Each role's responsibilities should still be explicit.
|
|
|
|
---
|
|
|
|
## Decision-making during an incident
|
|
|
|
**The IC's authority:**
|
|
|
|
- Call rollback or other mitigations
|
|
- Pull additional people in
|
|
- Escalate severity
|
|
- Make the call when unclear options exist
|
|
|
|
**Non-decisions to avoid:**
|
|
|
|
- "Let's wait and see" when mitigations are available and impact is occurring
|
|
- Discussing root cause while users are actively impacted (mitigate first)
|
|
- Premature resolution announcements before verification
|
|
- Death-by-committee (pull in lots of people, no one decides)
|
|
|
|
When in doubt: act. A wrong action that can be rolled back beats inaction while users suffer.
|
|
|
|
---
|
|
|
|
## Status page communication patterns
|
|
|
|
**Initial:**
|
|
> "We are investigating reports of [issue]. Updates to follow."
|
|
|
|
**Identified:**
|
|
> "We have identified the issue affecting [scope]. Engineers are working on a fix. Next update by [time]."
|
|
|
|
**Monitoring:**
|
|
> "A fix has been applied. We are monitoring to confirm resolution. Next update by [time]."
|
|
|
|
**Resolved:**
|
|
> "This incident has been resolved. Service has been restored. A full incident report will be posted within [timeframe]."
|
|
|
|
Patterns to avoid:
|
|
|
|
- Vague language ("experiencing some issues" - what kind?)
|
|
- Missing affected scope ("login is down" - everywhere or just one region?)
|
|
- Missing time commitments
|
|
- "Should be resolved soon" without verification
|
|
- Using "back up" before verification
|
|
|
|
---
|
|
|
|
## Workflow
|
|
|
|
1. **Acknowledge.** First responder acknowledges within target time.
|
|
2. **Assess severity.** Use the rubric. Open the appropriate response channel.
|
|
3. **Assign roles.** IC, comms, ops at minimum.
|
|
4. **Communicate.** Initial status update. Internal channel active.
|
|
5. **Investigate.** Logs, metrics, recent changes. The four most common causes: a recent deploy, a configuration change, a third-party dependency change, a load spike.
|
|
6. **Mitigate.** Stop the bleeding. Don't wait for full root cause.
|
|
7. **Verify mitigation.** Don't trust dashboards alone; test the user flow.
|
|
8. **Communicate resolution.** Internal and external.
|
|
9. **Close incident.** Final timeline noted. Action items tracked.
|
|
10. **Schedule AAR.** Within 1 to 2 weeks.
|
|
|
|
---
|
|
|
|
## Failure patterns
|
|
|
|
- **No clear IC.** Multiple people debugging in parallel, no coordination. Slower to mitigate, easier to make conflicting changes.
|
|
- **Skipping mitigation, going straight to root cause.** Users keep suffering while engineers debug.
|
|
- **Premature "all clear."** Announcing resolution before verification.
|
|
- **Communication silence.** Users don't know if anyone is working on it.
|
|
- **Status updates too vague.** "We're working on it" with no detail.
|
|
- **Speculating publicly about cause.** Often wrong, always damaging trust.
|
|
- **Pulling in too many people.** Coordination overhead exceeds value.
|
|
- **No scribe.** The timeline gets lost. AAR has to reconstruct from chat logs.
|
|
- **Skipping AAR for "minor" incidents.** Patterns get missed. Lessons get re-learned.
|
|
- **Blame culture.** People hide mistakes, incidents take longer.
|
|
|
|
---
|
|
|
|
## Output format
|
|
|
|
During an active incident: incident channel updates and status page updates as per the framework above.
|
|
|
|
After incident close: a brief incident summary feeding into the AAR.
|
|
|
|
```markdown
|
|
# Incident: [Brief title]
|
|
|
|
**Date:** [YYYY-MM-DD]
|
|
**Severity:** [SEV-1 / 2 / 3 / 4]
|
|
**Duration:** [Detection to resolution]
|
|
**Customer impact:** [Who, how many, how]
|
|
|
|
## Summary
|
|
[1 to 2 paragraphs]
|
|
|
|
## Timeline
|
|
[Timestamped events]
|
|
|
|
## Mitigation
|
|
[What was done]
|
|
|
|
## Action items
|
|
[Follow-ups, with owners]
|
|
|
|
## AAR scheduled for
|
|
[Date]
|
|
```
|
|
|
|
---
|
|
|
|