Risk Register Playbook

Guide Origin: Official | ArcKit Version: [VERSION]

/arckit:risk creates a comprehensive risk register following HM Treasury Orange Book principles for project and operational risk management.


Inputs

Artefact Purpose
Requirements (ARC-<id>-REQ-v1.0.md) Requirements that could be at risk
Stakeholder drivers Business context and risk appetite
Architecture diagrams Technical risks from design
Existing risk registers Organizational risk context

Command

/arckit:risk Create risk register for <project>

Output: projects/<id>/ARC-<id>-RISK-v1.0.md


Risk Register Structure

Section Contents
Executive Summary Overall risk profile and top risks
Risk Appetite Organization's tolerance for risk
Risk Categories Grouping of risks by type
Risk Register Detailed risk entries with scoring
Risk Treatments Mitigation actions and owners
Risk Monitoring Review schedule and escalation
Dependencies Cross-project and external risks

Orange Book 4Ts Risk Responses

Response Description When to Use
Tolerate Accept the risk Low impact, low likelihood
Treat Mitigate the risk Reduce likelihood or impact
Transfer Share the risk Insurance, contracts, third parties
Terminate Avoid the risk Remove the risk source entirely

Risk Scoring Matrix

Likelihood / Impact Very Low (1) Low (2) Medium (3) High (4) Very High (5)
Very High (5) 5 10 15 20 25
High (4) 4 8 12 16 20
Medium (3) 3 6 9 12 15
Low (2) 2 4 6 8 10
Very Low (1) 1 2 3 4 5

Risk Categories

Category Examples
Strategic Business case viability, stakeholder support
Delivery Timeline, resources, dependencies
Technical Technology maturity, integration complexity
Security Data breaches, cyber threats
Financial Budget overrun, funding uncertainty
Compliance Regulatory, legal, policy requirements
Operational Service availability, support capability

One-Page Workflow

Phase Key Activities ArcKit Commands
Discovery Define requirements and stakeholders /arckit:requirements, /arckit:stakeholders
Identification Identify and categorize risks /arckit:risk
Assessment Score and prioritize risks Review workshop
Treatment Define mitigations and owners Update risk register
Monitoring Regular review and reporting Governance meetings

Review Checklist

  • Risk appetite clearly defined and agreed.
  • All risk categories considered.
  • Each risk has likelihood, impact, and score.
  • All high/very high risks have treatment plans.
  • Treatment owners and deadlines assigned.
  • Dependencies on other projects captured.
  • Review schedule established.
  • Escalation thresholds defined.

Risk Entry Format

Field Description
ID Unique identifier (RISK-001)
Title Brief description
Category Risk category
Description Detailed explanation
Cause What could cause this risk
Effect Impact if risk materializes
Likelihood 1-5 score with rationale
Impact 1-5 score with rationale
Inherent Score Likelihood × Impact (before treatment)
Response Tolerate/Treat/Transfer/Terminate
Treatment Actions to address the risk
Owner Person accountable
Residual Score Score after treatment

Key Principles

  1. Risk-Informed Decisions: Use risk to guide project decisions.
  2. Proportionate Response: Treatment effort matches risk severity.
  3. Clear Ownership: Every risk has a named owner.
  4. Regular Review: Risks change; register must be living document.
  5. Escalation Culture: High risks escalate promptly to senior leaders.